Project Sunshine Drift
Project Summary
Project Sunshine Drift is a three-phase, 25 MW solar energy development paired with a 100 MWh Battery Energy Storage System (BESS), aimed at strengthening grid reliability and delivering clean, renewable power in San Bernardino County, California. The project reflects SolEnergy Solutions LLC’s long-term commitment to building a more sustainable energy future while ensuring efficient, dependable energy for local communities.
We’re working closely with California Independent System Operator (CAISO) to support a smooth and efficient interconnection process. At the same time, we’re actively coordinating with San Bernardino County to complete permitting and meet all regulatory requirements.
Sunshine Drift marks an important step in our broader growth strategy—with future phases and additional projects already on the horizon.
25 MW
100 MWh
Grid Interconnect

Project Benefits
Supports California’s Renewable Energy Goals
Contributing to the state’s net-zero carbon initiatives
Improves Grid Reliability & Energy Storage
BESS allows for energy distribution flexibility and peak demand management
Reduces Dependence on Fossil Fuel
Providing sustainable, locally produced energy
Economic & Environmental Impact
Creating local jobs and reducing carbon emissions in San Bernardino County
25 MW Solar + 100 MWh Battery Storage
2024
Project Kickoff
Start of Phase 1: 4 MW PV + 16 MWh battery system
Land preparation, planning, and pre-construction underway
Early-stage permitting and interconnection coordination
2025
Construction & Engineering
Progress on interconnection and permitting
Community and stakeholder engagement continues
2026
Finalization of Phase 1
Procurement and installation of solar modules and battery systems
Testing and commissioning of systems
Final inspections and performance validation
Preparation for commercial operation
Q1 2027
Phase 1 COD
Phase 1 begins commercial operations
Supplying clean energy to the grid
Post-2027
Phase 2 Development
Launch of Phase 2 to expand capacity
2028
Phase 3 Launch
Final phase begins
2030
Full Build Out
Project reaches full build-out: 25 MW PV + 100 MWh BESS